I-15 Construction

All posts are those of the individual authors and the owner of this site does not endorse them. Content should be considered opinion and not fact until verified independently.

August 23, 2004 04:42PM
http://www.dot.ca.gov/dist8/projects/15_improve.htm

Interstate 15 Major Improvements from the Cajon Pass to State Route 58 north of Barstow

Completed

A northbound truck climbing lane in the Cajon Pass from State Route 138 to Oak Hill Road.
This 7.3-mile project cost $6.4 Million, was started in April 2003 and completed in May 2004.
Funding: STIP, TEA21.

To Be Completed

1) Add mixed flow lanes in both directions between Mojave Drive and the junction of SR 58;
add southbound auxiliary lane between D Street and Mojave Drive, rehab pavement northbound
between Stoddard Wells Road and Dale Evans Parkway. This 28.7-mile, $120 Million project
started in the spring of 2002 and is scheduled to be complete in the summer of 2005.
Funding: STIP, SHOPP, LLP, DEMO (State of California and State of Nevada).

2) Reconstruct the Main Street interchange in Hesperia, and widen the overcrossing to six lanes.
This $9.5 Million project started in September 2003 and is scheduled to be complete in spring 2005.
Funding: STIP, TEA21, City of Hesperia.

3) At the Mojave Drive overcrossing in Victorville, reconstruct the interchange, including bridge
widening and signal installation. This $3.7 Million project is scheduled to start in the fall of 2005
and be complete in the fall of 2007.
Funding: MINOR A, ISTEA, City of Victorville.

4) In Victorville from State Route 18 to north of the Mojave Drive overcrossing, upgrade median
barrier and pave median. This 2.6-mile, $3.5 Million project is scheduled to start in
winter 2007 and be complete in summer 2007.
Funding: SHOPP.

5) In Victorville from just north of the Mojave Drive interchange to Stoddard Wells Road,
add a northbound mixed flow lane with an auxiliary lane, and reconstruct the D and E street
interchanges and the Stoddard Wells Road interchange. This 3.5-mile, $63.6 Million project
is scheduled to start in the winter of 2008 and be complete in the summer of 2010.
Funding: STIP, LLP.


Revised August 2004
SubjectAuthorViewsPosted

I-15 Construction

Rick 1069August 23, 2004 04:42PM

Re: I-15 Construction

Rick 538August 23, 2004 04:43PM

Re: I-15 Construction

Paul P. 566August 24, 2004 12:49PM

Re: I-15 Construction

LaughingBear 593August 24, 2004 05:45PM

Paving Bowen Ranch Rd.?

mojavegreen 994August 25, 2004 06:05PM